Weston,Ma
2008 DPW CONSTRUCTION SCHEDULE
June 16, 2008 Sidewalk Reconstruction begins on Boston Post Road
from Concord Road to Route 20
June 25, 2008 Sidewalk Reconstruction on School Street begins
from Maple Road to Route 20
June 24-25, 2008 Reconstruction of Sunset Road begins
June 25-26, 2008 Reconstruction of Crescent Street begins
June 26 thru July 3 Reconstruction of High School, Middle School
Roadways and Case House Parking Area begins
July 7, 2008 Mill and Asphalt Overlay of Hillcrest Road begins
July 9, 2008 Mill and Asphalt Overlay of Chestnut Street begins
July 11, 2008 Mill and Asphalt Overlay of Ridgeway Road and
Oxbow Road begins
Please Note: schedule is subject to weather and circumstances beyond our control